I recently reviewed some contractor schedules and I was surprised that the schedulers had changed the Schedule Options, When scheduling progressed activities use option from the default of Retained Logic to Actual Dates and they both ended up with meaningless programs because their circular relationships were no longer being identified.
This paper aims to explain the difference between the way Schedule Options, When scheduling progressed activities use option of Retained Logic, Progress Override and Actual Dates calculate, so when people change the default of Retained Logic they will be aware of the risks they are running.
Click here to download a pdf of this paper>>>>>
Eastwood Harris Resources
Accelerate your understanding of scheduling software to advance your scheduling career and be able to prepare better schedules with Eastwood Harris books, training courses and online videos on the following software packages:
- Microsoft Project,
- Oracle Primavera P6 and
- Elecosoft (Asta) Powerproject
Online video training is available through Udemy through following these links:
Please follow these links:
- Eastwood Harris books and training materials are available here https://www.eh.com.au.
- Eastwood Harris inhouse, one-to-one and public training courses are offered through Primaskills Pty Ltd, more details here>>>>.
- Resources for Oracle Primavera P6 users such as third party software that works with P6 and technical papers on Primavera P6 at https://primavera.com.au/.
Paul E Harris
Director Eastwood Harris Pty Ltd
5 June 2023