An absolute finish date may be imposed on the project using the Project Window, Dates tab. Imposing a Must Finish By date makes Primavera calculate the late dates from the Must Finish By date rather than the calculated early finish date. Click on this link to see an article on how this P6 operates
To see more explanations like this then please consider purchasing Microsoft Project, Oracle Primavera P6 or Elecosoft (Asta) Powerproject books by Paul Harris which is available in many formats, paperback, spiral, Kobo, Kindle and iTunes.
These books are intended to be used:
- As a self-teach book and user guide, or a training manual for a three-day training course.
- PowerPoint slide shows are available for training companies to purchase and pdf versions are available to educational organisations.
More information and links to sellers at this web site:
https://www.eh.com.au/PP6V18PPM.html
Accelerate your understanding of scheduling software to advance your scheduling career and be able to prepare better schedules with Eastwood Harris books, online videos available through Udemy and training material on:
Details at https://www.eh.com.au
Paul E Harris
Director Eastwood Harris Pty Ltd