Primavera P6 Software Tips and tricks – Setting Up a New Project

Set Up a New Project Using Primavera P6 Software

To review or modify some of the basic Project or EPS information entered when a project was created, ensure that the Project Details form is displayed in the bottom of the screen:

  • Highlight a project or EPS Node,
  • The project must be open to edit some project data,
  • You must also have the appropriate access rights to edit data,
  • Select View, Show on Bottom, Details and click on the General tab:

set up project in primavera p6

  • The Risk Level may be used to sort and filter Projects and EPS Nodes.
  • The Project Leveling Priority is used when leveling a project to reduce peaks in resource requirements. Value of 1 is the highest and 100 the lowest.
  • Check Out Status enables the user to determine if the project is checked in or checked out (New to Version 4.1). Checked Out By and Date Checked Out enables the user to establish if the project is currently checked out.

Eastwood Harris Supplies Project Management Training Manuals, Project Management Training Presentations and Consulting on Primavera P6 and Microsoft Project 2010 across Australia.


Leave a Reply

  

  

  

You can use these HTML tags

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>