Activity Types and Milestones in Primavera P6 Version 8.2

primavera p6 wbs activitiesActivity Types and Milestones in Primavera P6

An Activity may be assigned one of the following default Activity Types using the drop down box in the Project Defaults tab:

  • Finish Milestone
  • Level of Effort
  • Resource Dependent
  • Start Milestone
  • Task Dependent
  • WBS Summary
TASK TYPE DESCRIPTION
  • Task Dependent
These Activity Types have a duration and will only calculate the duration using the assigned calendar even when one or more resources are assigned to an activity.
  • Resource Dependent
These Activity Types have a duration and will calculate the duration only using the calendar assigned to the activity when NO resources are assigned to the activity.

These activities acknowledge Resource Calendars when resources are assigned.

This is similar to an Independent Activity Type in P3 and SureTrak.

They acknowledge the Activity calendar to calculate the Early Start date.

  • Level of Effort – LOE
This Activity type is similar to P3 and SureTrak Hammock activities. It spans from the start or finish of one or more predecessor activities to the start or finish of one or more successor activities which are linked by relationships.
  • Start Milestone
A Start Milestone has a start date and no finish date and is scheduled at the start of a time period and may not be assigned Resources.
  • Finish Milestone
A Finish Milestone has a finish date, no start date and is scheduled at the end of a time period and may not be assigned Resources.

Changing a milestone from Start to Finish would not affect a schedule when all the tasks are on one calendar but would move the milestone from the start of a day to the finish of the previous day.

  • WBS Summary
This Activity type calculates in the same way as P3 and SureTrak WBS activities and they span all activities with the same WBS code, but without relationships that are used with LOEs.
primavera p6 version 8-2 info button A Milestone has zero duration and is used to mark the start or finish of a major event. Primavera differentiates between Start and Finish Milestones in the same way as P3 and SureTrak, where a Start Milestone has a start date and no finish date and a Finish Milestone has a finish date and no start date. This is unlike Microsoft Project, which only has one type of Milestone. Later versions of Microsoft Project allow milestones with durations.